A company to count. Orrery, 210 people on the payroll and 28 contractors on top. One hundred and forty systems on the asset list, of which 31 hold customer data. Twenty-four people can reach production. Seventeen other companies sit somewhere inside the delivery of the product.
That is four categories, each with a number against it, and nothing else. No controls yet, no frameworks, no opinions. The question in front of you is where to draw a line through those numbers.
Predict
A boundary is four counts, not a paragraph.
Systems — the things that run. The useful subset is the ones that hold or touch customer data, because that subset is defensible in a sentence.
People — the ones who can reach what is inside. The useful subset is production access, for the same reason.
Contractors — people who are not on the headcount and are on the access list. They belong to the people count or to nobody.
Other companies — the suppliers inside your delivery. They belong to the systems count or to nobody.
Writing the four numbers down is the entire method. Everything after it is arguing about where the line goes, which is an argument you cannot have until the numbers exist.
The model holds those four counts and one control for where the line falls. The line has four positions and each one adds exactly one category to the one below it, so a notch is a defined step rather than a gesture. For now, leave the line at its narrowest and move only the counts.
Scope arithmetic
Hypothetical model, not a forecast
Counts the systems and people inside a stated certification boundary, the ones left outside it, and how far the count moves when the boundary shifts by one category.
It assumes
It ignores
At this position of the line, four of the six counts do nothing at all. Find them by moving each one on its own and watching the count inside the line. Then use the two that do work to take the count inside the line past 100.
| Where the line falls: 0 narrowest, 3 everything | Systems inside | People inside |
|---|---|---|
| 0 | 31 | 24 |
| 1 | 31 | 52 |
| 2 | 48 | 52 |
| 3 | 157 | 238 |
Not there yet — keep moving the controls.
Fifty-five things inside the line and three hundred and forty outside it. The share inside is the number a buyer reading your certificate would want and never gets, because no document in either framework reports it.
Four of the six counts were inert. The total number of systems did nothing; so did the total number of people, the contractors and the other companies. At the narrowest line the only two counts that moved anything were the two subsets — systems holding customer data, people with production access.
That is worth sitting with, because it inverts the usual instinct. Your boundary at its narrowest is not sensitive to how big your company is. It is sensitive to how good your filters are, and a filter is a sentence somebody wrote. Change systems holding customer data from 31 to 86 and you have doubled the count inside the line without adding one machine to the estate.
Which is also the first place this goes wrong in real life: the subset count is usually guessed, upward, by somebody being careful. Being careful about the filter is the most expensive form of caution available here.
Check
Three things are missing from the four categories, and each is missing for a different reason.
Nested suppliers — the companies your suppliers use. They are inside your boundary as far as your customers are concerned, whatever your sentence says, and there is no count of them anywhere because nobody publishes one.
Systems nobody put on the list. The free tool somebody connected to production with an API token has no invoice and therefore no row in the asset inventory. It is outside your boundary by omission rather than by decision, and those two are not the same thing to defend.
Effort. The count is systems and people, and effort does not scale with the count. One noisy legacy system with three owners and no logging can cost more hours than forty quiet managed services. The count is the right first number and the wrong last one.